The diameter 700 mm portion of the pressure shaft for Tokheim Hydropower Plant over a length of 1120 m in Odda is finished.
Break trough at planned position is appreciated by the customer as the intake shall be established under challenging conditions in a terrain with limited availability.
Next step is now to do reaming up to 1200 mm and then to install steel lining before the power plant is ready for commissioning.