HIGH SPEED DRILLING – 400 m for Einungstølsåna Hydropower Plant in 6 days

  • Writer: Norhard AS
    Norhard AS
  • Sep 16, 2021
  • 1 min read

Pressure shaft for Einungsølsåna Hydropower Plant:

Diameter: 1200 mm

Length: 400 m

Customer: Sunnhordaland Kraftlag


The directional drilling of the diameter 400 mm pilot tunnel was finished in less than one week.


Maximum drilling length over a 12 hours shift was 49 m which is new Norhard ROP record.

Next step - reaming up to diameter1200 mm before installation of steel lining - diameter 1100 mm.


 
 
 